Grierson Hill LRT Slope Stabilization: Remediated with NPA Geocells

___
Stratum Logics designed a successful soil stabilization solution using NPA geocell technology. The iconic Grierson Hill in Edmonton had lost its beauty after expansion works were done for the LRT. After multiple attempts to restore its allure by the initial contractor, Stratum Logics was consulted for a more advanced solution.

CORE CONCERNS:

Slope Stability, Slope Protection, Durability

APPLICATION:

Slope Reconstruction

CONDITIONS:

Unstable Slope

LOCATION | DATE:

Edmonton, Alberta | Sept, 2021

PROJECT OVERVIEW

___
Stratum Logics was commissioned to provide a slope stabilization solution to
support vegetative regrowth. This project involved stabilizing the steep embankments along the North Saskatchewan River and around the tunnel portal for Edmonton’s LRT expansion at Grierson Hill.

The slope posed significant challenges due to its steep inclines, with some areas exceeding 70°. Through advanced engineering and the application of novel polymeric alloy (NPA) geocell technology, Stratum Logics successfully restored the slope’s stability and facilitated the rejuvenation of its natural vegetation.

 

 

 

 

 

Area of LRT Slope that needed remediation

CHALLENGE ACCEPTED

___
The solution factored in the following:

■ Steep Inclines:
Incline ranged between 55 and 83 degrees, presenting significant soil retention and revegetation challenges.

■ Anchoring Limitations:
Limited options for anchoring J-hooks due to restricted areas and no use of tension tendons.

■ Load Distribution:
Ensuring the geocell system can effectively distribute loads without imposing additional stress on the slope.

■ Seasonal Factors:
Addressing risks of freeze-thaw cycles, snowloads, and potential soil slippage.

THE PROBLEM

___
The slope was unable to support soil load and revegetation as the initial project designer underestimated the challenging process of revegetation post-construction. As a result, the once-green slope that existed became an eyesore to the community.

Despite numerous attempts to replace topsoil that would allow for revegetation, the contractor was unsuccesful due to the formidable incline reaching a daunting angle of 83º in some areas. As a result, a long-term solution to support vegetative growth was needed.

Traditional stabilization methods, such as tendon anchoring, were not feasible due to the presence of utility lines and limited anchoring opportunities at the crest. Additionally, the risk of soil slippage caused by freeze-thaw cycles, snow loads, and surface runoff further complicated the design requirements.

The project required a solution capable of retaining a 200mm thick layer of plantation soil for vegetative growth while ensuring stability on slopes exceeding natural soil stability limits (30° inclination). Until the vegetation could be fully established, artificial support was necessary to prevent erosion and maintain slope integrity. Stratum Logics designed and implemented a successful NPA geocell solution that achieved the desired result.

PROJECT AT A GLANCE

Condition of the LRT slope before NPA geocell installation

Condition of the LRT slope before remediation

Installation of the NPA geocell layer

Installation of the NPA geocell layer

Infilling of the NPA geocell layer with top soil

Infilling of the NPA geocell layer with top soil

NPA geocell job complete

NPA geocell job complete

Regrowth the following spring

Regrowth the following spring

Full vegetation in the summer

Full vegetation in the summer

PROJECTS SPECS

Total Area Icon

TOTAL AREA

___

1400sqm
Slope

Slope icon

INCLINE

___

55 to 83 degrees
Slope

NPA geocell icon

NPA GEOCELL SPECS

___

250 x 210mm pocket size
150mm height
>750MPa at 30 degrees dynamic modulus

Geocell Dimensions

Rebar icon

ANCHORS

___

10M rebar
with stainless steel zip ties
Reinforcement

Aggregate infill icon

INFILL

___

>200mm
Top Soil Thickness

OUTCOMES AND BENEFITS

___
■ Erosion Control:
The geocell system provided long-term soil stability,
eliminating future costs associated with soil replacement.

■ Cost Efficiency:
Optimized anchor usage reduced construction time and labor costs.

■ Sustainability:
The solution minimized environmental impact and promoted green
construction.

■ Long-term Performance:
The geocell properties, such as UV resistance and minimal creep
deformation, ensured lasting stability.

RESULTS AND OBSERVATIONS

___

■ Vegetative Regrowth:
Vegetation successfully established itself within 6 months,
covering the slope and restoring its natural beauty.

■ Durability:
Despite rain events and freeze-thaw cycles, no significant failures were observed during the first year.

■ Minor Adjustments:
Areas with low soil thickness were hydro seeded, ensuring complete coverage.

■ Innovative Techniques:
The use of wire nets bridged non-anchor zones effectively, demonstrating the potential for broader applications.

REFERENCE

Further technical details are documented in the paper titled “Stabilizing Green Steep Slope
Around Tunnel Portal Using Polymeric Alloy Geocell,” published at the International Conference on Geosynthetics (ICG), 2023

Do you have a slope that needs remediation?

Request a Consultation

26550 Acheson Road,
Acheson, AB T7X 6B2

1 (877) 683 8459 or
1 (780) 418 1957

info@stratumlogics.com